6. Commencement Stage

Share

6.1 Online submission to Building Control Authority

The online submission at commencement stage will typically include the following:

a) Commencement Notice (or 7 Day Notice);

b) plans, calculations, specifications and particulars as are necessary to outline how the building proposed works or building will comply with the requirements of the Second Schedule to the Building Regulations relevant to the works or building concerned, and including:

  • general arrangement drawings – including plans, sections and elevations;

  • a schedule of such plans, calculations, specifications and particulars as are currently designed or are to be prepared at a later date;

  • the completion of an online assessment, via the Building Control Management System, of the proposed approach to compliance with the requirements of the Second Schedule to the Building Regulations (Parts A to M);

c) the preliminary Inspection Plan prepared by the Assigned Certifier;

d) a Design Certificate (with a schedule of Ancillary Certificates by members of the design team, who should also sign their certificate);

e) a Notice of Assignment of Assigned Certifier by the Building Owner;

f) a Notice of Assignment of Builder by the Building Owner;

g) form of Undertaking by the Assigned Certifier;

h) form of Undertaking by the Builder and

i) the appropriate fee.