What is the role of the Building Control Authority at completion stage?

Share

At completion stage, the Building Control Authority validates the submission of the Certificate of Compliance on Completion by:

  • Checking that the CCC was completed properly and signed by the appropriate people.

  • Checking that the CCC Annex was completed properly.

  • Checking that the Inspection Plan as Implemented was completed properly.

  • Checking that there are no unresolved matters relating to requests under Section 11 of the Act, Enforcement Notices, or conditions attached to Fire Safety or Disability Access Certificates etc.

The BCA also includes details of the CCC in the Statutory Building Control Register of Building Control Activity.